Schedule Management
Lead and Lag
Lead
An acceleration of the successor activity.
Example: Finish-to-Start with -2 days lead means the successor can start 2 days before the predecessor finishes.
Use case: Painting can start 2 days before all drywall is complete (start painting finished rooms while others are still being drywalled)
Lag
A directed delay between activities.
Example: Finish-to-Start with +3 days lag means the successor must wait 3 days after the predecessor finishes.
Use case: Concrete must cure for 3 days before construction can continue
Exam Tips
- Critical path = longest path = shortest project duration
- Crashing = add resources = increases cost
- Fast tracking = do things in parallel = increases risk
- Always crash/fast track critical path activities first
- Lead = negative lag (acceleration)
- Lag = positive delay (waiting period)
- Float = flexibility in scheduling
